#buildinginghana #lifeinghana #building #construction #ghanaians #buildingworks
In todays video, i bring to you the full cost estimate of the Project Ground Floor till finishing stage. This event took place from May 2022 - November 2024. I appreciate each and everyone for been part of the journey.
*Ground Floor Construction Costs Till Finishing*
*Structural Phase 1 (May-Dec 2022)*
- Ground Floor to Casting: 34,300 GHS
- Blocks Laying to Lentil: 34,050 GHS
- Decking (Rods Works): 36,322 GHS
- Decking (Carpentry Works): 23,190 GHS
- Decking (Concrete Casting): 27,140 GHS
- Electricals (Phase 1): 2,270 GHS
- Plumbing (Phase 1): 2,660 GHS
- Total: 159,932 GHS
*Structural Phase 2 (Jan-Feb 2023)*
- Electricals (Phase 2): 5,280 GHS
- Windows Burglar + Frames: 10,900 GHS
- Plastering & Corrections: 31,460 GHS
- Windows (Alluminium): 12,317 GHS
- Plumbing (Phase 2): 10,739 GHS
- Doors + Fixing + Frames: 13,332 GHS
- Total: 84,028 GHS
*Finishing Phase 1 (Feb-Mar 2023)*
- Electricals (Phase 3): 24,840 GHS
- Laying Earth & Breakers: 1,720 GHS
- Ceptic Tank: 22,356 GHS
- POP Installation: 28,290 GHS
- Porch Balustrade + Exit Burglar: 7,570 GHS
- A/C Conduit Piping: 6,150 GHS
- Total: 90,926 GHS
*Finishing Phase 2 (Mar-Dec 2023)*
- Tiles: 74,365 GHS
- Lights, Switches & Other Elec: 20,188 GHS
- Plumbing (All Pipes to Ceptic): 8,343 GHS
- Water Plumbing: 4,087 GHS
- Wall Skimming + Graf + Labor: 12,040 GHS
- TV Stand + Electrical's: 5,500 GHS
- Dining Arc Design: 2,500 GHS
- Trap Door + Buttons + Lock: 2,500 GHS
- Polytank Structure: 18,046 GHS
- POP Update: 6,685 GHS
- Fittings & Accessories: 26,308 GHS
- Master Bed Room Door: 2,540 GHS
- Total: 183,102 GHS
*Total Ground Floor Construction Cost*
159,932 + 84,028 + 90,926 + 183,102 = *517,988 GHS*
*GHS : 517,988*
*USD : $35,120*
*POUNDS : £28,550*
Thank you for watching.