Continued from the previous clip
It is Contract 4-7 Saraburi-Kaeng Khoi
The construction is continuing..
From the beginning of the contract, at the piers that will span the Saraburi station building
The beginning on the west side has casted the segment boxes that are attached to the piers
The other one on the east side is also preparing to pour concrete..
At the Saraburi high-speed train station
It is continuously progressing, both the work of pouring the runway on the piers
The work of making the building foundation
Including casting the beams at the ticket office
At the piers, the balanced cantilever beams crossing the Saraburi bypass road 362 on the east side
The casting of the cantilever beams from the pier segment boxes
On the east side, 2 segments can be extended
The area of the new station junction is also continuous..
Both the office building work
The work of casting the runway on the piers
The work of casting additional twin piers
Is also ongoing
Including casting Pier segment that straddles Kaeng Khoi station..
Start assembling the steel frame that will be cast..
In any case, go watch the clip..